HELLO + WELCOME we're so pumped to share with you the build of our new home the Lexia by Beechwood Homes. Thanks for stopping by!
26 February 2015
24 February 2015
16 February 2015
8 February 2015
4 February 2015
We've been Framed :O
Exciting times!! The frame has almost been completely constructed!
We might add some extra noggins to the walls to hold the wall hung TV's, some large photo frames in the dining alcove and entry, towel hooks in the ensuite and bathroom and a few other bits a pieces so we don't have the problem of not being able to hang things where we want them once the walls are up! Little bit of pre-planning can go a long way later down the track.
I think once the windows are in and the roof is on we will be able to get a good feel for the rooms.
We might add some extra noggins to the walls to hold the wall hung TV's, some large photo frames in the dining alcove and entry, towel hooks in the ensuite and bathroom and a few other bits a pieces so we don't have the problem of not being able to hang things where we want them once the walls are up! Little bit of pre-planning can go a long way later down the track.
I think once the windows are in and the roof is on we will be able to get a good feel for the rooms.
Elevation A
Garage
Front
Living + Dining + Windows
Living
Kitchen
Roof Trusses
19 January 2015
We've been slabbed!
The biggest thrill of the past week has been the news that our concrete slab was finally underway and would be poured on Monday 19/01.
Things finally seem to be happening on the block since site works commenced before Christmas. The ground was still so wet after all of the rain we've been having so work on the slab couldn't commence.
Things finally seem to be happening on the block since site works commenced before Christmas. The ground was still so wet after all of the rain we've been having so work on the slab couldn't commence.
5 December 2014
Site works
Of course this stuff happens when we are away, not sure what day it started. Thanks to our awesome neighbour for the pics! Land is now scrapped! It was so unexpected (exciting but unexpected) we thought site works would start after christmas. I may have freaked slightly, all I could think about was wanting to get photos and having missed half of the site works! But of course I was way ahead of myself and freaking for no reason the block had only been cut and filled and no plumbing or slab work had been done yet which meant that I hadn't missed any important photo opportunities hehe.
So, BWH has cut and filled the block and advised that a slab should be down this week. Hope this rain doesn't ruin the plans.
17 November 2014
It's the final countdown!!!!!!!!!!!!!!
I am very excited to share that our file has been transferred to the Construction team. Our 28 day countdown began on the 14 Nov!!
We also signed off on our final plans yesterday and this morning received a call from the lovely LH at BWH to say that everything has been ordered! Really happy with how the plans have turned out after all our changes. Fingers crossed it all translates once it's up!
The actual commencement date will depend on the weather and our individual site conditions. Heavy rain or an extended period of rain and any subsequent retention of water in the soil may postpone the site works.
Plans
Elevations
We also signed off on our final plans yesterday and this morning received a call from the lovely LH at BWH to say that everything has been ordered! Really happy with how the plans have turned out after all our changes. Fingers crossed it all translates once it's up!
The actual commencement date will depend on the weather and our individual site conditions. Heavy rain or an extended period of rain and any subsequent retention of water in the soil may postpone the site works.
Plans
Elevations
16 October 2014
Color Selections
Ahh the biggest and most time consuming selection appointment! We started our appointment at 10.00am and finished just before 4pm!
We upgraded ALOT but very happy with everything! We finished off our colours and electrical, deciding to put down lights throughout and power points in the contract so we don't have to pay South West Electrical separately.
We couldn't get the contract today as we made some changes to the overhead cupboards to make them all flush line and we couldn't get a price from the kitchen company to go into the contract so hopefully can get it by tomorrow to give to Westpac Monday.
Check out the Colour Selection tab to view our selections!
Check out the Colour Selection tab to view our selections!
1 October 2014
CDC Approval!!
Got home today and waiting for us was a big thick package from Beechwood!!!
Inside was a lovely letter saying we have CDC approval! So happy, I'm not sure when they are planning to call me to book in colours so I'm just going to call them tomorrow, time to get this show on the road!
Inside was a lovely letter saying we have CDC approval! So happy, I'm not sure when they are planning to call me to book in colours so I'm just going to call them tomorrow, time to get this show on the road!
22 September 2014
Come on CDC approval!
Day 8 of CDC and we are eagerly awaiting confirmation that we are approved and we can move on to colours!
We have spent those CDC days double checking the house internals making sure that everything is even and we haven't forgotten anything. Some thing that has been bothering me is the kitchen breakfast bar, on the current plans it sticks out 400mm past the fridge wall. I originally thought it was a great idea, upon thinking realistically I realise it is probably taking up way too much living/dining space :/
So with that in mind we set out to work out how we could get more living space and decided to decrease the WIL/WIP 400mm. If you see on the plans below we will still get an OK size WIP at around 875mm x 2000. The Living/Dining becomes 5165mm instead of 4765mm :)
With the WIL I think it would be better to swap the door and have it open outwards. I know it's considerably smaller than the previous one but we would much rather the living/dining space.
Any feedback would be appreciated! We have made over 45 variations to the Lexia to make it our own plan and the worst thing is not knowing how it's all going to look or if an area is too small. I think in the long run we would regret not making the Living/Dining room bigger if we could.
We have spent those CDC days double checking the house internals making sure that everything is even and we haven't forgotten anything. Some thing that has been bothering me is the kitchen breakfast bar, on the current plans it sticks out 400mm past the fridge wall. I originally thought it was a great idea, upon thinking realistically I realise it is probably taking up way too much living/dining space :/
So with that in mind we set out to work out how we could get more living space and decided to decrease the WIL/WIP 400mm. If you see on the plans below we will still get an OK size WIP at around 875mm x 2000. The Living/Dining becomes 5165mm instead of 4765mm :)
With the WIL I think it would be better to swap the door and have it open outwards. I know it's considerably smaller than the previous one but we would much rather the living/dining space.
Any feedback would be appreciated! We have made over 45 variations to the Lexia to make it our own plan and the worst thing is not knowing how it's all going to look or if an area is too small. I think in the long run we would regret not making the Living/Dining room bigger if we could.
12 September 2014
CDC
On Wednesday we received a text message from BWH that our plans have been lodged to CDC!
This will take 10 days, not sure if it's days or business days so we will see.
Once we have approval from CDC we will be able to make an appointment with headoffice for colours and contract signing then the 28 days countdown to site start begins!
While we wait for contract signing we need to confirm our colours, we thought we had everything set until we (I) hehe started watching this season of The Block.
We love everything Chris and Jenna and Max and Karstan have produced. The kitchen and bathrooms are to die for! We have already chosen the same bathroom tiles but in Matte finish and for the kitchen we have black benchtops and a mirror splashback already selected but we had chosen Cavia Lini for the cabinets. Thinking now to change to the same cabinet colour 'Sepia Oak" - will just need to confirm upgrade price :/
Karstan and Max's bathroo
Karstan and Max's bathroom have produced so far, there kitchen and bathrooms are to die for!The funny thing is we must have the same taste as we had chosen the exact bathroom tiles but in Matte finish and we also have black benchtops and mirror splashback for the kitchens.
26 August 2014
14 August 2014
Settlement Approaching!
While we wait for settlement, I have been busy organising the Planning Certificat e S149(2) for BW. They need it to lodge the final plans to CDC. It was received today from Wollongong Council!
6 August 2014
REGISTRATION!
WE HAVE REGISTERED as at 10.25am this morning! So happy and relieved that it is out of Stocklands hands and they can no longer F@#k it up!
So where to from here?
Well we have notified Beechwood and Westpac and settlement will occur in 14 days and then we are official mortgagees!
So where to from here?
Well we have notified Beechwood and Westpac and settlement will occur in 14 days and then we are official mortgagees!
31 July 2014
Plan Changes
Variations we made to plans:
- Flip entrance door
- Centre all windows
Facade
- Provide moroka finish to front of master suite and patio (including brick pier) returning 1000mm approx down side of Master Suite $324
- Provide 2 x AAA1912 windows to master suite front wall in lieu of standard $902
- Provide a 4.89 (max) wide sectional panel door in lieu of two standard including engineer's designed steel beam $1784
- Provide Hume 820mm XS28 entrance door in lieu of standard $0
- Provide a Gainsborough Trilock Omni 8905 double cylinder in lieu of standard $611
- Provide colourgrain timber look alike doors (steel) to garage sectional panel door $372
Kitchen/Laundry
- Decrease WIP + WIL depth to 875mm to allow breakfast bar to align with fridge cavity end wall
- Relocate fridge cavity to laundry wall adjacent to laundry door 990mm x 850mm $$
- Decrease breakfast bar 15cm to 2730mm to increase space between fridge and breakfast bar to 950mm
- Decrease rear kitchen bench to 2730mm
- Increase WIP door to 720mm
- Decrease Laundry door to 720mm
- Widen WIL and WIP 10cm to compensate for 620mm door; reducing space between bench and breakfast bar to 1050mm $
Living/Dining
- Provide 2 x ATD2009 (850mm) Double Hung windows (windows to sit on floor adjacent to Alcove) to Meals area in lieu of previously requested ATD1907 (724mm) $
- Provide under eave alcove $
- Provide stacker door 3195mm in lieu of standard $
Bathroom
- Provide AS1416 bathroom window in lieu of standard $
- Move the Bathroom window down the wall to sit 100mm above the bath frame
- Flip the bathroom
- Increase bathroom 210mm into Bed 3 to incorporate 1670 bath
Bedrooms
- WIR 820mm door change to 720mm door
- Relocate WIR door 100mm towards garage
- Increase WIR by 60mm in width (new size 1580mm x 2250mm) making Ensuite 1800mm x 2250mm
- Decrease sq set entrance to Ensuite from 900mm to 800mm - set 50mm from from back of WIR.
- Cavity door to WIR (720mm) $
- Provide AS0616 window to Bed 4 in lieu of stanard
- Provide stacker door 3195mm in lieu of standard $
- Flip entrance door
- Centre all windows
Facade
- Provide moroka finish to front of master suite and patio (including brick pier) returning 1000mm approx down side of Master Suite $324
- Provide 2 x AAA1912 windows to master suite front wall in lieu of standard $902
- Provide a 4.89 (max) wide sectional panel door in lieu of two standard including engineer's designed steel beam $1784
- Provide Hume 820mm XS28 entrance door in lieu of standard $0
- Provide a Gainsborough Trilock Omni 8905 double cylinder in lieu of standard $611
- Provide colourgrain timber look alike doors (steel) to garage sectional panel door $372
Kitchen/Laundry
- Decrease WIP + WIL depth to 875mm to allow breakfast bar to align with fridge cavity end wall
- Relocate fridge cavity to laundry wall adjacent to laundry door 990mm x 850mm $$
- Decrease breakfast bar 15cm to 2730mm to increase space between fridge and breakfast bar to 950mm
- Decrease rear kitchen bench to 2730mm
- Increase WIP door to 720mm
- Decrease Laundry door to 720mm
- Widen WIL and WIP 10cm to compensate for 620mm door; reducing space between bench and breakfast bar to 1050mm $
Living/Dining
- Provide 2 x ATD2009 (850mm) Double Hung windows (windows to sit on floor adjacent to Alcove) to Meals area in lieu of previously requested ATD1907 (724mm) $
- Provide under eave alcove $
- Provide stacker door 3195mm in lieu of standard $
Bathroom
- Provide AS1416 bathroom window in lieu of standard $
- Move the Bathroom window down the wall to sit 100mm above the bath frame
- Flip the bathroom
- Increase bathroom 210mm into Bed 3 to incorporate 1670 bath
Bedrooms
- WIR 820mm door change to 720mm door
- Relocate WIR door 100mm towards garage
- Increase WIR by 60mm in width (new size 1580mm x 2250mm) making Ensuite 1800mm x 2250mm
- Decrease sq set entrance to Ensuite from 900mm to 800mm - set 50mm from from back of WIR.
- Cavity door to WIR (720mm) $
- Provide AS0616 window to Bed 4 in lieu of stanard
- Provide stacker door 3195mm in lieu of standard $
16 June 2014
Still waiting...
So here we are mid June and we are still waiting for registration. Stockland have told us they will be lodging to LPI by the end of the week - at this point we will believe it when we see it! Once it's lodged to LPI it will be around 4 weeks until registration!
Also, we are still waiting on the final plans back from BW. We sent the plans back on the 2/6 as Bed 3 & 4 windows were off center. I hope there are no more mistakes as BW admin processes are way to long.
In the meantime we decided to change the external colours, we just felt that the outside didn't reflect the inside and we wanted it to all be similar colours.
Hopefully I will have some good news at the end of the week!
Also, we are still waiting on the final plans back from BW. We sent the plans back on the 2/6 as Bed 3 & 4 windows were off center. I hope there are no more mistakes as BW admin processes are way to long.
In the meantime we decided to change the external colours, we just felt that the outside didn't reflect the inside and we wanted it to all be similar colours.
Hopefully I will have some good news at the end of the week!
I also used floorplanner.com to do a mock up of the internals.
30 May 2014
FINAL House Plans!!!
Yes we have plans and FINAL plans!
We are really happy but will sit on it until Monday before we sign off on it to make sure there is nothing we've missed as once we sign off it's $250 to change!
Things we need to check:
- Location of shower heads and mixer
- Location of laundry taps
- Location of manhole
- Size of M/W cavity
- Size of bin cupboard
- Size of M/W cavity
- Size of bin cupboard