HELLO + WELCOME we're so pumped to share with you the build of our new home the Lexia by Beechwood Homes. Thanks for stopping by!
23 April 2015
16 April 2015
Locked up and out!
So went to the house today not expecting to get in but the plasterer was there and let us through. Was pleasantly surprised to see the stairs are in and tiles delivered ready to start laying next Wednesday.
Also I received an email from Beechwood that the kitchen and vanities will be installed by the end of the week!
Also I received an email from Beechwood that the kitchen and vanities will be installed by the end of the week!
![]() |
Laundry and Bathroom Floor Tile |
13 April 2015
10 April 2015
3 April 2015
27 March 2015
11 March 2015
5 March 2015
4 March 2015
Day 6 of bricking and electrical rough in...
Bricking is almost finished and I can't believe they are nearly finished after only 7 days of bricking. They only need to cap off the windows, install the steel beam over the garage and finish off the brick pole in the Alfresco and facade pole.
Electrical rough in is complete!
Alfresco P/P |
Living Room |
Media |
Hills Home Hub 1000 |