Timeline


19/06/13 - Purchased land
31/01/14 - Beechwood tender received
10/02/14 - Tender Variation 2 received
22/02/14 - Deposit to Beechwood Homes
13/03/14 - Tender Variation 3 received
14/04/14 - Pre-lim plans received
08/08/14 - Land Registered
14/08/14 - Planning Certificate S149(2) received
26/08/14 - External selections sent to Stockland
09/09/14 - Stockland External Approval received
10/09/14 - Plans sent to CDC
25/09/14 - CDC Approval
16/10/14 - Colour Selection Appointment
05/11/14 - Contract signed
07/11/14 - Site pegged
13/11/14 - Westpac Commencement Letter Received
14/11/14 - BWH advise construction to commence within 28 business days
25/11/14 - Site Cut
29/11/14 - Site Fence and Port-a-loo on site
02/12/14 - Piering complete
15/12/14 - Drains dug and form work started
17/12/14 - Plumbing complete
12/01/15 - Rio/Rods/Concrete delivered
19/01/15 - Slab Poured
28/01/15 - Electrical Appointment
30/01/15 - External plumbing completed
02/02/15 - Frames and windows delivered
03/02/15 - Frames erected
05/02/15 - Roof Trusses delivered
08/02/15 - Roof complete
11/02/15 - Windows installed
12/02/15 - Fascia and gutters installed
18/02/15 - Roof completed
20/02/15 - Bricks delivered
24/02/15 - Bricks started
05/03/15 - Electrical rough in complete
06/03/15 - Bricking complete
11/03/15 - Eaves complete
14/03/15 - Bricks cleaned
19/03/15 - Wet room waterproofing started
20/03/15 - Wet room waterproofing complete
23/03/15 - Insulation delivered
25/03/15 - Insulation complete
25/03/15 - Gyprock delivered
30/03/15 - Gyprock complete and plastering started
07/04/15 - Cornice complete
13/04/15 - Architraves/Skirting installed
16/07/15 - Stairs installed/tiles delivered
22/04/15 - Kitchen delivered and installed
08/05/15 - Benchtops installed
08/05/15 - Interior painting complete
20/05/15 - Electrical complete
21/05/15 - Bathroom tiling complete
25/05/15 - Fit out complete
04/06/15 - Air con installation complete
04/06/15 - Garage door fitted
12/06/15 - Water tank installed
17/06/15 - Shower screens/mirrors installed
19/06/15 - Living/Dining Tiling started
20/06/15 - Living/Dining Tiling complete
27/06/15 - Practical Completion Walkthrough
03/07/15 - Handover